🚧 Overview of the I‑30 Rockwall Bridge Project
The I‑30 expansion project across Lake Ray Hubbard in Rockwall County is a major infrastructure upgrade led by TxDOT. It includes new frontage road bridges and widening main lanes to improve traffic flow and resilience across the lake (rockwall.com).
Segment 1: Bass Pro Drive to Dalrock Road
Segment 2: Dalrock Road to State Highway 205 (via Horizon Road)
Segment 3: SH 205 to Hunt County line
This corridor upgrade covers approximately 16 miles, crossing Rockwall & Dallas counties (rockwall.com, Construction Equipment Guide, Wikipedia).
💰 Project Costs & Funding
The project is funded through TxDOT’s Texas Clear Lanes congestion relief initiative, prioritizing non-tolled expansion to relieve congestion in the DFW metro area (NCTCOG).
Breakdown by segment:
Segment 1 (Bass Pro Drive–Dalrock Rd): about $142 million (TxDOT FTP)
Segment 2 (Dalrock Rd–SH 205): roughly $317 million (Construction Equipment Guide)
Segment 3 (SH 205–Hunt County line): about $343 million (Construction Equipment Guide)
➡️ Total estimated cost: ~$802 million for the full corridor from Bass Pro Dr to the Hunt County line (Construction Equipment Guide).
Note: Earlier planning documents estimated around $552 million overall for a similar scope in 2017, but cost estimates have since risen due to escalating work and broader scope (keepitmovingdallas.com, rockwall.com).
🏗 Timeline: When It Started & When It Ends
Segment 1:
Construction began: July 2021
Estimated completion: August 2024 (weather permitting) (TxDOT FTP, rockwall.com)
Segment 2:
Let for construction: Fall 2022
Started work: March 2023
Planned finish: January 2027 (rockwall.com, Construction Equipment Guide)
Segment 3:
Let for construction: Fall 2022
Started work: September 2023
Planned completion: December 2027 (rockwall.com)
So the full corridor is expected to be complete by late 2027 (NCTCOG).
🚦 Traffic Capacity & Road Layout
Upon completion, the I‑30 corridor will offer enhanced road capacity:
Main lanes:
8 lanes (4 lanes each direction) from Bass Pro to SH 205
6 lanes (3 each direction) from SH 205 to Hunt County line (keepitmovingdallas.com)
Frontage roads:
Continuous frontage roads with up to 6 lanes total (i.e. 3 lanes per direction) over the lake in Segment 1
Reconstructed and added frontage roads in Segments 2 and 3 to allow cross-lake connectivity even if main lanes are blocked (rockwall.com)
Managed lanes? The ultimate conceptual plan envisions 2 managed + 2 general-purpose lanes each direction plus two‑lane one‑way frontage roads. That would allow future conversion of lanes into tolled express lanes or high‑occupancy lanes if funded (Rockwall County).
Will it be a toll road?
No. This project is entirely non‑tolled, funded via Texas Clear Lanes. There are no tolls on the new bridges or main lanes (NCTCOG).
Managed lanes are conceptual and not currently tolled, but the design does allow future conversion if funding and policy change (Rockwall County).
👷 Workforce & Construction Scope
While exact crew headcount is not publicly detailed, project scale gives a sense of workforce demands:
Segment 1: built 185 columns for eastbound frontage bridge, 166 for westbound → total ~351 columns
Bridge deck area of ~944,000 sq ft and ~73,000 sq ft of concrete paving (sema.inc)
Across all segments: 1,089 columns across four frontage road bridges, with over 76,000 ft of drill shaft foundations (deepest ≈110 ft).
Materials moved include 17,132 cu yds of dredged lakebed (Construction Equipment Guide).
Massive scale suggests hundreds to thousands of workers across both contractors (SEMA for Segment 1, Williams Brothers for Segments 2/3) spanning multiple years.
📅 Detailed Timeline & Milestones
| Phase / Segment | Limits | Start Date | Cost Approx. | Completion Target |
|---|---|---|---|---|
| Segment 1 | Bass Pro Dr → Dalrock Rd | July 2021 | ~$142 M | August 2024 |
| Segment 2 | Dalrock Rd → SH 205 | Construction start: Mar 2023 | ~$317 M | January 2027 |
| Segment 3 | SH 205 → Hunt County Line | Construction start: Sept 2023 | ~$343 M | December 2027 |
🛠 What Has Been Built & What’s Next
✅ Completed or Nearing Completion (Segment 1)
Eastbound frontage road girders and main lanes poured
Westbound frontage road girders installed
Bayside Drive bridge, Dalrock interchange, retaining/sound walls in place
Traffic switches expected in late summer – early fall 2025 for the Horizon bridge shift (Construction Equipment Guide, Rockwall County, rockwall.com)
🔨 Ongoing & Upcoming Work (Segments 2 & 3)
Scatter of drill shafts in water, ramp modifications, frontage road bridges underway
Reconstruction of I‑30 main lanes from six → eight (Segment 2) and four → six (Segment 3)
Framing interchanges, widening former causeways, prepping for deck pours and paving through 2026–27 (Construction Equipment Guide)
🚗 Traffic Volumes & Benefits
Prior to construction, the corridor carried ~40,000 vehicles/day in Rockwall area (Construction Equipment Guide).
Dalrock Rd interchange itself serves 25,000 vehicles/day, a major connector to SH 66 and north Rockwall County (NCTCOG).
Benefits expected:
Reduced congestion and backups when incidents occur on lake bridges
Redundancy via frontage roads ensures cross-lake connectivity if main lanes are blocked
Improved emergency access and response times across the lake
Better regional capacity for population growth and traffic volumes (sema.inc, Construction Equipment Guide)
🎯 Summary & Key Points
Estimated total cost: ~$802 million for the full corridor expansion from Bass Pro Drive to Hunt County line.
Construction start: July 2021 for Segment 1; Segments 2 & 3 began in March & September 2023
Estimated completion: Late 2027 for all work
Traffic capacity: 8 main lanes Bass Pro → SH 205; 6 lanes further east; full frontage road bridges
Tolls?: None—this is a non-tolled TxDOT project
Workforce estimate: Likely hundreds or more working over multiple years; contractors: SEMA and Williams Brothers
🎉 Emoji Recap & Highlights
🚧 Big infrastructure rebuild across Lake Ray Hubbard
💰 ~$800 million total investment
📆 Started July 2021 → Finishes by late 2027
🚗 8 main lanes + frontage road bridges = major capacity boost
❌ No tolls, though design allows future managed-lanes conversion
👷 Hundreds–thousands of workers involved over years of construction
🧩 Conclusion
The I‑30 Rockwall bridge project is a transformative infrastructure investment for the Dallas‑Rockwall region, offering expanded capacity, greater redundancy across the lake, and a modernized corridor designed to meet growth demands. With a clear timeline, hefty funding, and no tolls, it represents a major achievement in North Texas transportation planning and engineering.
If you’d like even deeper info—such as schematics, traffic studies, or updates on specific interchange designs—just let me know!
